Automatic Pool Covers for New Construction
New construction is the only stage where undertrack, a sized housing, and drainage can be built in before coping is set. The cover is a construction sequence, not a finish option added at tile. Lock track type, box size, and power or hydraulic provision on the drawings. This page is the coordination list for builders and owners.

What to lock before excavation finishes
You need a housing location, a track type, a drain path out of the box, and a drive decision that matches the equipment room. Changing those after the beam is poured is how projects stall or get forced onto top track.
| Stage | Lock this | Too late when |
|---|---|---|
| Design | Shape, end wall, track family, drive | Shell is already in the ground |
| Excavation | Box footprint and drain rough-in | Deck forms are set |
| Bond beam / coping | Guide elevation and access | Coping is set with no service path |
| Deck and lid | Lid plane and trip edge | Finish is already chosen against the box |
| Commissioning | Water at operating level | Cover runs before the pool is at spec level |
Why new-build still uses a decision tree
If the pool is freeform or vanishing-edge, new construction does not automatically make an automatic cover honest. The leading edge still has to travel a pair of guides. Run the same shape review you would run on a retrofit, then use the extra time to hide the track if the geometry works.

Trade split on a new pool
The builder owns shell geometry, box rough-in, and deck elevation. The electrician owns the circuit and disconnect. The cover installer owns tracks, roller, fabric, limits, and owner briefing. Write that split into the bid so the gap does not sit between contracts.
What to read with this page
Use the parent hub for the product family, then stay inside this cluster for the decision you still have open. The related cards below are the three pages that usually settle the next question without sending you back to a generic search.
If travel is already unsafe, leave the guide and open repair. If you need a preliminary system read, use request system advice with photos of both ends and both long sides.
Hold points the builder should put on the calendar
Cover design should land before excavation locks the box. Track family should land before coping forms. Power or hydraulic sleeves should land before the pad is poured. Commissioning waits for operating water, not for a punch-list week when the deck is already stained.
| Hold | If you miss it | Catch-up |
|---|---|---|
| Housing end | Equipment pad fights the box | Relocate pad or accept a worse lid |
| Drain | Box becomes a pond | Core later through finished work |
| Track family | Coping does not hide the guide | Switch to top track |
| Disconnect | Cover ships with no legal power | Electrician return visit |
常见问题
- When should the cover installer visit the site?
- At design, at box rough-in, at coping, and at commissioning. One visit after the deck is finished is how undertrack gets lost.
- Can we decide the drive after the shell is in?
- Only if the housing and equipment room were sized for both. Otherwise the late choice forces electric or a messy hydraulic line run.
- Can the plumber size the box drain?
- The plumber can run the pipe. The cover drawing should name the outlet, the slope, and whether the box can flood the motor space.
- When do I order fabric on a new pool?
- After finished waterline dimensions exist, not from the first excavation sketch. Shells move.